What is PERT and how does it differ from a purely deterministic CPM estimate?

PERT uses optimistic, most likely, and pessimistic estimates to compute a weighted expected duration; it provides a probability-based schedule, while CPM uses fixed estimates.

PERT incorporates uncertainty in activity durations by using three-point estimates—optimistic, most likely, and pessimistic—for each activity. These estimates are combined into a weighted expected duration for the activity, commonly TE = (O + 4M + P)/6, which gives a mean duration and a measure of variability (variance = ((P - O)/6)^2). Because each activity now has a distribution rather than a single fixed time, the overall project duration becomes probabilistic, allowing you to estimate the probability of finishing by a certain date.

CPM, on the other hand, uses a single fixed duration for each activity, yielding a deterministic schedule with a definite critical path and no explicit probability distribution for completion times.

So the described distinction—using optimistic, most likely, and pessimistic estimates to compute a weighted expected duration and producing a probability-based schedule, versus relying on fixed estimates—is why that option is correct.

PERT ignores uncertainty.

PERT and CPM are identical.

PERT uses only most likely estimates.

Want more questions?

All options are one-time payments.

$25.99

30 day pass for new members

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
$59.99$171.99 usd

6 month DELUXE pass (most popular)

Full access FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • $171.99 usd value for $59.99! You save $106!
  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 6 months of full access
  • Ultimate digital PDF study guide included
  • Priority support
$15.99 $24.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy